Lake Travis High School Athletic Facilities Upgrades

The addition of a 3,300 SF pre-fabricated, two-story press box features a film deck, camera deck, kitchen, mechanical and technology spaces. Additional enhancements to the school’s athletic facilities included new lockers in the freshman locker room. Stadium upgrades also included new scoreboards at the varsity stadium, baseball field, softball field and at the upper track stadium. The baseball field underwent lamp replacement to improve it’s field lighting. Additional ADA improvements were identified and corrected by Flintco to meet and exceed current accessibility requirements.

Details

Location

Austin, TX

Cost

$1,387,079

Size

6,900 SF

Completion

September 2012

Owner

Lake Travis ISD

Architect

Pfluger Associates Architects

Role

Prime Contractor

Delivery Method

General Contracting