Phased Construction and Security in a High-Risk Federal Facility

Modern glass office building on a clear day, with blue reflective windows surrounded by a grassy area.

Challenge

The FAA Multi-Purpose Building in Oklahoma City houses the backup data center supporting national airspace operations for all U.S. commercial and military aircraft. Flintco was tasked with completely gutting and modernizing the 211,000 SF facility—stripping it to the structural frame and rebuilding it from the ground up—while keeping the data center operational 24/7 throughout a four-year renovation. With approximately 400 FAA employees occupying upper floors and the site located on active airport property, uninterrupted operations, security, and safety were non-negotiable.

The project scope included major seismic upgrades below the water table in contaminated soil, lead and asbestos abatement, and renovation work both inside and beneath the data center. Access to the data center itself was strictly prohibited, even as its entire exterior, including the main entrance, was demolished and rebuilt.

Solution

Flintco developed a phased construction strategy that prioritized risk mitigation. Work began in the basement, allowing seismic and structural upgrades to be completed first. Work then progressed from the exterior inward, enabling early enclosure of the building and minimizing exposure to weather, dust, and security risks.

Security planning was fully integrated into each phase. Emergency action plans were aligned with FAA protocols and used owner-provided maps that included muster points and alternative response procedures. Temporary enclosures, dust screens, and dedicated fire watch coverage were installed around the data center during exterior wall work. Continuous communication with site personnel ensured safe movement throughout the facility and prevented unauthorized access to active construction zones.

Result

The phased, security-driven approach enabled continuous operations and occupancy, delivering the project on schedule with zero OSHA recordable incidents over 1,698 days of construction.



RELATED ARTICLES

  • Apr 13 2026

    Flintco’s Phillip Gunderson Named AGC Oklahoma Project Manager of the Year

    Project Manager Phillip Gunderson was named 2025 Project Manager of the Year by the Associated General Contractors of Oklahoma (AGC…

    READ MORE
  • Apr 03 2026

    RSU Hosts Groundbreaking for Robson Center for Science and Technology

    Rogers State University took a step into the future this week with a groundbreaking ceremony for the new Robson Center…

    READ MORE
  • Mar 30 2026

    Flintco-Mortenson JV breaks ground on $900M Oklahoma City NBA arena

    The reigning NBA champions have tipped off work on their new home. Major project stakeholders attended the Thursday groundbreaking of the…

    READ MORE

You Bring The Vision.

We’ll Make It Happen.